Numerical Modelling Approach For Assessment Of Factor Of Safety Of Ribs In Continuous Miner Depillaring Panels – A Case Study Of Churcha Mine

Jump To References Section

Authors

  • ,IN
  • ,IN
  • ,IN

DOI:

https://doi.org/10.18311/jmmf/2021/29409

Keywords:

Numerical Modelling, FOS, Geo-mining, Threshold Limit, Augment, Fenders.

Abstract

Continuous miner (CM) technology is being adopted as a successful mass production technology for working coal seams by underground (UG) method in India. This technology is getting established as an ideal option to meet the objectives of the high output, productivity, and safety with a moderate level of investment. In UG coal mines, the success of the bord and pillar method of working largely depends on the depillaring operations, as the maximum coal recovery is achieved during these operations. CM panels in India, especially during depillaring operations, experience in numerous problems like premature collapses, overhanging roof, partial extraction in a panel, etc., as some of the significant parameters influencing the stability of UG structures are still not standardised. As such, there is an urgent need to have a better understanding of the behaviour of UG structures, overlying roof and sidewalls for efficient and effective designing of the depillaring operations with particular reference to geo-mining conditions. This paper deals with a brief review of the strata control problems faced in CM workings and study of stress distribution for assessing the optimum factor of safety (FOS) of the ribs in CM depillaring panels by using numerical modelling as a tool. This model can be applied for assessing the pattern in variation of FOS of the ribs in CM depillaring panels for safe extraction of coal or, alternatively, for designing the ribs in such panels by fixing the threshold limit of the FOS of ribs for a particular geo-mining condition.

Downloads

Download data is not yet available.

Metrics

Metrics Loading ...

Published

2022-01-24

How to Cite

Prasad, S. S., Sinha, R. K., & Rambabu, B. (2022). Numerical Modelling Approach For Assessment Of Factor Of Safety Of Ribs In Continuous Miner Depillaring Panels – A Case Study Of Churcha Mine. Journal of Mines, Metals and Fuels, 69(11), 379–388. https://doi.org/10.18311/jmmf/2021/29409

 

References

Agrawal, H., Singh, S. K., Mandal, P. K. and Singh, A. P. (2015): 3Dimensional numerical modelling: An effective enabler for CM deployment in coal seams. Journal of Mines, Metals and Fuels, 63(5–6), 111–118.

Chase, F. E., McComas, A., Mark, C. and Goble, C. D.(1997): Retreat mining with mobile roof supports. Proceedings of the New Technology for Coal Mine Ground Control in Retreat Mining, NIOSH IC, 9446, 74–88.

Christopher mark, tuchman j. rober. (1997). I c 9446 Proceedings/: New Technology for Ground Control in Retreat Mining. NIOSH, IC 9446.

Das, A. J., Mandal, P. K., Paul, P. S., Sinha, R. K. and Tiwari, S. (2018): Rock mechanics considerations for mechanised extraction of an inclined coal seam. Recent Challenges in Mining Industry (RCMI 2018), Organtzed by Mining Engineers’ Association of India Dhanbad Chapter in Association with CSIR-Central Institute of Mining and Fuel Research Dhanbad 826015, Jharkhand, India, 121–130.

Ghasemi, E., Ataei, M., Shahriar, K., Sereshki, F., Jalali, S. E. and Ramazanzadeh, A. (2012): Assessment of roof fall risk during retreat mining in room and pillar coal mines. International Journal of Rock Mechanics and Mining Sciences, 54, 80–89. https://doi.org/10.1016/ j.ijrmms.2012.05.025

J.D.Inch, j.D. Stone, I.D.Brumby, C. J. B. (1980). The use of continuous miners in South African coal mines. The Journal of The South African Institute of Mining and Metallurgy, 5–21.

Jawed, M., Sinha, R. K. and Sengupta, S. (2013): Chronological development in coal pillar design for bord and pillar workings/ : A critical appraisal. 5 (January), 1–11. https://doi.org/10.5897/JGMR12.010

Kumar, A., Kumar, D., Verma, A. K., Singh, A. K., Ram, S. and Kumar, R. (2018): Influence of Overlying Roof Strata on Rib Design in Mechanised Depillaring.Journal of the Geological Society of India, 91(3), 341– 347. https://doi.org/10.1007/s12594-018-0860-7

Lind, G. H. (2002a): Coal pillar extraction experiences in New South Wales. Journal of The South African Institute of Mining and Metallurgy, 102(4), 207–215.

Lind, G. H. (2002b): Key success elements of coal pillar extraction in New South Wales. The Journal of The South African Institute of Mining and Metallurgy, (June), 199–206.

Mandal, P. K., Kumar, R. and Sinha, A. (2006): Stateofart vis-à-vis Indian scenario of application of continuous miner based mass production technology. Journal of Mines Metals and Fuels, (December).

Mandal, P. K., Singh, A. K., Kumar, N. and Singh, R.(2004): Strata Behaviour Investigations Of India’s First Depillaring Face With Continuous Miner And Shuttle Car, Minetech, 25(6), 3–12.

Mark, C, Pappas, D. M. and Barczak, T. M. (1969): ground fall accidents in US coal mines. NIOSH, IC 9446.

Mark, Christopher. (2017): Ground control during pillar recovery with continuous miners. In Advances in Coal Mine Ground Control. https://doi.org/10.1016/B978-008-101225-3.00010-4

Mark, Christopher and Zelanko, J. C. (2001): Sizing of final stumps for sale pillar extraction. Proc. 20h Int.Conf. on Ground Control in Mining, Morgantown, WV, USA, 1–8.

Mishra, A. K., Mishra, A. K. and Rout, M. (2013): Blast-Induced Caving from Surface over Continuous Miner Panel at a 110m Cover in an Indian Mine. 1861– 1870. https://doi.org/10.1007/s13369-012-0386-z

Mukhopadhyay, S. and Sharma, S. (2017): A case study illustration of the layout and support in an Indian coal mine with difficult roof condition where continuous miner is in operation. In Naj Aziz and Bob Kininmonth (Eds.), Proceedings of the 17th Coal Operators’ Conference, Mining Engineering, University of Wollongong, 8-10 February 2017, (February), 8–10.Retrieved from http://ro.uow.edu.au/cgi/ viewcontent.cgi?article=2310&context=coal

Ram, S., Kumar, D., Konicek, P., Singh, A. K., Kumar, R., Singh, A. K. and Singh, R. (2015): Rock mechanics studies during continuous miner based coal pillar extraction in Indian coalfields. Transactions: A Technical Publication of the MGMI, 111, 89–114.

Satyanarayana, I. and Budi, G. (2015): Evaluation of induced vertical stress during depillaring in blasting gallery panel workings. International Journal of GeoEngineering. https://doi.org/10.1186/s40703-0140002-z

Singh, A. K., Singh, R., Maiti, J., Kumar, R., & Mandal, P. K. (2011): Assessment of mining induced stress development over coal pillars during depillaring. International Journal of Rock Mechanics and Mining Sciences, 48(5), 805–818. https://doi.org/10.1016/ j.ijrmms.2011.04.004.

Singh, R., Mandal, P. K., Singh, A. K., Kumar, R., & Sinha, A. (2011): Coal pillar extraction at deep cover: With special reference to Indian coalfields. International Journal of Coal Geology, 86(2–3), 276– 288. https://doi.org/10.1016/j.coal.2011.03.003

Singh, S. K., Agrawal, H. and Singh, A. P. (2017). Ribstability: A way forward for safe coal extraction inIndia. International Journal of Mining Science and Technology, 27(6), 1087–1091. https://doi.org/10.1016/j.ijmst.2017.06.007

Vervoort, A. and Jack, B. (1992): Analysis of sidewall fracturing and spalling during. The Journal of TheSouth African Institute of Mining and Metallurgy, 92(January), 3–11.

Churhca Mine Management and Annual Safety WeekReport, Churcha Mine (2016)

Annual Report, 2019-20, Official Website, Ministry of Coal, Govt. of India.